● Capacity:Total construction area: 116,384 square meters
● Owner: Guigang Integrated Traditional Chinese and Western Medicine Orthopedic Hospital
● Construction site: Guigang, Guangxi
● Honor: Feasibility study report of the project won the Award for Excellent Engineering Consulting Achievement in Guangxi in 2022
● Project Highlights:Construction start: June 2022,Completion & acceptance: March 2025,Operation date: September 2026,Operational capacity: 1,500 beds,Target classification: Level 3 integrated traditional Chinese and Western medicine general hospital