● Capacity: Total investment: 40 million RMB,Total GFA: 7,440.32 m²,Production workshop: 6,958.74 m²,Grain unloading shed: 481.58 m²
● Owner: Guangxi Zehua Silk Road Trading Co., Ltd.
● Construction site: Qinzhou, Guangxi, China
●Project Highlights: The project is located within the Beibu Gulf (Qinzhou) International Grain Processing Industrial Park, with two grain silos of 5,000 tonnes each and six grain silos of 250 tonnes each.
●Project overview: The project is located within the Beibu Gulf (Qinzhou) International Grain Processing Industrial Park, with a total investment of 40 million yuan. The total construction area amounts to 7,440.32 m², including a production workshop of 6,958.74 m², a grain unloading shed of 481.58 m², as well as 2 grain silos with a capacity of 5,000 tons each and 6 silos with a capacity of 250 tons each.